Key takeaways
- Sunshine Coast rail: detailed design has begun on Stage 2, from Caloundra to Birtinya, after the design and pre-construction contract was awarded in November 2026.
- Major construction on The Wave is expected to start in early 2027, subject to Australian Government environmental approvals.
- Stage 2 still depends on funding. The federal government has not yet committed money to it.
- Stage 1 has $5.5 billion committed, split evenly between the Australian and Queensland governments.
- Stages 1 and 2 are expected to support 3,300 regional jobs.
The Sunshine Coast is the largest urban area in Australia without a direct passenger rail connection to its nearest capital city. Sunshine Coast rail plans to change that are now gathering pace, and locals have until 23 December 2026 to comment on the project’s environmental report.
The Queensland Department of Transport and Main Roads (TMR) says work is moving ahead on The Wave, a new heavy rail line from Beerwah to Birtinya. Major construction is expected from early 2027, provided the Australian Government grants environmental approval. Once the line is running, TMR says it will save more than 45 minutes at peak times compared with driving.
What the Sunshine Coast rail line will include
- Stage 1 will add 19 kilometres of dual-track rail from Beerwah to Caloundra. It will upgrade Beerwah station and build new stations at Bells Creek (Aura) and Caloundra.
- Stage 2 would extend the line about 7 kilometres from Caloundra to Birtinya. It includes new stations at Aroona and Birtinya, and a tunnel of roughly 1 kilometre beneath Little Mountain.
- At Birtinya, the line is planned to connect with Stage 3, a metro-style service running to Sunshine Coast Airport via Mountain Creek and Maroochydore.
The consortium SunLinQ won the Stage 2 design and pre-construction contract in November 2026, and detailed design is now under way. Residents will be asked for their views on the Stage 2 station precincts in early 2027.
Funding, jobs and homes
- The Australian and Queensland governments have each pledged $2.75 billion for Stage 1, bringing its total funding commitment to $5.5 billion.
- Queensland has set aside a further $40 million to speed up planning and prepare Stages 2 and 3 for the market.
- Both stages are expected to be built at the same time, subject to funding. The federal government has not yet committed money to Stage 2.
- TMR expects the first two stages to support 3,300 regional jobs.
- TMR also says the project will help deliver more than 3,000 affordable and diverse homes around the new stations over the coming decade.
What happens next for Sunshine Coast rail
The construction timing still depends on Australian Government environmental approval. The Draft Public Environment Report is open for public review until Wednesday 23 December 2026. You can read it on the Queensland Publications Portal, at local libraries, or at the project’s information centres in Caloundra and Beerwah. Consultation on the Stage 2 station precincts follows in early 2027.
Also read: ACCC excessive pricing crackdown targets 8 everyday grocery groups at Coles and Woolworths
General information only, not legal advice. Check the official source before acting.
Source: Queensland Department of Transport and Main Roads. Licence: CC BY 4.0.